Building Renovation Information

We are excited to announce that the renovation project is set to begin on Monday, November 18!

 

As you can imagine, there will be some temporary challenges prior to and during our construction period. I wanted to give you some of the details and changes in order to make this season a successful one. Check back often for updated information.

 

 Week of 11/11

A) We will be clearing current suites A,B, and C

B) Tear down chairs/tables from the community center to be stored on campus

C) Relocate praise team equipment( praise team will oversee), AV equipment. No earlier than Thursday evening.

D) All other items to be moved by volunteers after Thursday of that week.

E) All stuff not needed for interim time will be stored in a pod on campus

 

Effective 11/17-conclusion of construction, the interim worship center will be used as followed:

     A) Sunday School 9

     B) Worship Service 10

     C) Korean Service 1

     D) Women's study continues at same time as before, to be held in community center

     E) Men's Monday night study at normal time

     F) Tuesday's Home school not in session until Jan

     G) Thursday's Home school will need set up and take down assistance only on 12/5

 

    All church fellowships during the construction period may be relocated to homes but will not be held in the community center during construction.

 

  No additional functions will be authorized at WSF unless approved by Elders/trustees.

 

     We want to thank everyone in advance for your flexibility and "Sweet Spirit"

 

More details to come!